Form 5

A Form 5 is a notification of competed service pipe connections that a SLP must use to tell Hafren Dyfrdwy which meters have been installed at each property.  This must be sent to Hafren Dyfrdwy within 5 days of making a service connection.

Hafren Dyfrdwy expect the minimum information for each plot to be completed on a Form 5:

  1. the Hafren Dyfrdwy reference number(s)
  2. the plot numbers to be connected
  3. the date of connection  
  4. the postal address 
  5. the occupier’s details, if known 

If the SLP has also installed the meter we also expect:

  1. the date the meter was installed
  2. the meter location 
  3. the meter size
  4. the meter serial number
  5. the meter reading